Engineering works to the 100-year-old Grade II listed structure, Corporation Road Bridge, are continuing. The steel work repairs are ongoing to both sides of the bridge deck. Primer and coatings of paint are also being applied to sections of the…
Works to Grade II listed structure, Corporation Road Bridge, have been progressing. The steel work repairs are ongoing to both sides of the bridge deck. Application of the primer and paint coatings has also been ongoing along with required preparation…
Restoration and repair works to Grade II listed structure, Corporation Road Bridge, have been progressing. Engineers on site will be carrying out work over the a number of weekends in March, taking advantage of expected low tide levels, to continue…
Refurbishment works to the iconic Corporation Road Bridge in Grimsby are progressing. Grit blasting works to the undersides of the bridge for spans 1, 2, 3 and 4 have allowed a detailed inspection of the structure, and this revealed an…
Restoration works to Grade II listed structure, Corporation Road Bridge, are progressing. Grit blasting is continuing on both the sub and superstructure of spans three and four of the bridge. Essential scaffolding and encapsulation works are also being undertaken to…
Representatives from North East Lincolnshire Council (NELC), Equans and Spencer Group welcomed members of the media to Corporation Bridge on Tuesday 10 October. Spencer Group explained the works and the reason for the extension to the programme and delayed reopening…
Corporation Bridge will no longer reopen in December 2023 after its condition has been found to be much more severe than originally expected. Multi-disciplinary bridge works specialist Spencer Group was appointed contractor for the works in November 2022, with works…
https://youtu.be/ppTN2QAjm8Y The essential heritage restoration works at Corporation Road Bridge, which will preserve the structure for future generations, is progressing. 50 steel deck plates on Corporation Road Bridge have now been replaced, a further 10 were lifted for a more…
The Leader of North East Lincolnshire Council and the portfolio for environment and transport attended Corporation Bridge on Friday 21 July to carry out a site visit with specialist contractor Spencer Group and the council’s delivery partner Equans. Updates were…
As scaffolding is erected on Corporation Bridge for works to progress, take a look at the structure from above. The below drone footage has been filmed by Spencer Group, the specialist contractor appointed to carry out the major restoration works.…
Corporation Road Bridge will be fully closed on Wednesday 5 July to allow for further scaffolding to be installed as works progress. All the steel deck plates on the bridge have now been grit blasted. Some of the steel deck…
Scaffolding is currently being erected at Corporation Bridge to provide access to the underside and harder to reach areas of the bridge in a safe and controlled manner. This then allows the grit blasting, detailed inspections, and painting of the…
Spencer Group, the specialist contractor currently working on the major restoration of Corporation Bridge, have shared drone footage of the lift that took place on Wednesday 5 April 2023. The lift took place to carry out weight testing to help…
A bridge lift took place on the iconic landmark on Wednesday 5 April 2023 to carry out weight testing to help assist specialist contractor Spencer Group with the weight balancing design works. Following the bridge weight test, the next section…
Works on Corporation Road Bridge are well underway. The asphalt surface of the bridge and the concrete carriageway deck has been removed down to its steel plates. The steel deck plates have been shot blasted and detailed inspections are now…
Essential restoration works to Grimsby’s Corporation Road Bridge are safeguarding the landmark structure for future generations and providing a boost to the local economy. In the words of specialist contractor Spencer Group, find out more about the major restoration of…
“Corporation Bridge is one of Grimsby’s survivors and a reminder of our town’s great maritime past,” says David Ornsby, operations manager at Grimsby Fishing Heritage Centre and part of the Special Interest Group for Corporation Bridge. “The bridge is one…
Work is well underway on Corporation Road Bridge as contractor Spencer Group have finished their site setup for the major restoration works. The tarmac surface of the bridge has been planed off and the concrete deck removal has commenced. Upcoming…
Work is underway to restore the iconic Corporation Road Bridge to maintain and protect in for many years to come. Representatives from North East Lincolnshire Council, Spencer Group and Equans attended the bridge on Monday 6 February to mark the…
Work has started on the major restoration of Corporation Road Bridge today, Monday 6 February. Multi-disciplinary bridge works specialist Spencer Group is now on site as the scheme gets underway. The full restoration will include key structural works, as well…